Location Asaluyeh Energy Zone, Persian Gulf
Sazeh Tadbiran successfully executed the complete engineering design, precision CNC fabrication, and on-site installation of the large-span barrel vault space frame roof for the Asaluyeh Petrochemical Industrial Storage and Process Hall. The project began with comprehensive 3D structural, thermal, and wind-load modeling in SAP2000 to create a completely unobstructed interior volume capable of housing massive automated stacker-reclaimer machinery and bulk material stockpiles. Based on these computational insights, our team engineered a high-rigidity double-layer MERO arch grid that eliminates internal columns and maximizes industrial storage capacity.
As a result of this turnkey industrial solution, the facility achieved a high-clearance, column-free operational envelope engineered to withstand one of the harshest industrial and marine climates in the world. During the manufacturing phase, Sazeh Tadbiran utilized hot-forged CK45 solid spherical nodes and applied a specialized chemical-resistant electrostatic powder coating system to combat extreme coastal humidity, airborne sulfur compounds, and industrial fumes. Every stage—from automated factory welding and 100% ultrasonic NDT checks to rapid 100% bolted field assembly—was executed under strict HSE and international petrochemical standards.
Engineering Proposal & Industrial Solution
The primary engineering objective was to deliver a high-clearance, column-free barrel vault roof structure capable of spanning wide industrial storage bays while resisting severe petrochemical corrosion and supporting overhead conveyor loads.
The implemented solution encompassed 3D elastic and thermal stress analysis in SAP2000, precision CNC machining of hot-forged CK45 spherical nodes, and heavy-duty anti-corrosive powder coating. Crucially, because the MERO system utilizes 100% bolted connections with Grade 10.9 high-tensile bolts, Sazeh Tadbiran erected the entire roof structure with zero on-site welding or hot-work hazards—ensuring full compliance with strict petrochemical HSE fire-safety regulations.
The implemented solution encompassed 3D elastic and thermal stress analysis in SAP2000, precision CNC machining of hot-forged CK45 spherical nodes, and heavy-duty anti-corrosive powder coating. Crucially, because the MERO system utilizes 100% bolted connections with Grade 10.9 high-tensile bolts, Sazeh Tadbiran erected the entire roof structure with zero on-site welding or hot-work hazards—ensuring full compliance with strict petrochemical HSE fire-safety regulations.
Project Technical Requirements
Project Engineering Methodology
An HSE-compliant turnkey workflow—engineered for extreme industrial durability, chemical corrosion resistance, and zero-weld site installation.
Analyzed severe thermal stresses, coastal wind pressures, and suspended conveyor loads in SAP2000 according to AISC standards.
Manufactured hot-forged CK45 nodes and tubular members protected by heavy-duty chemical-resistant electrostatic powder coating.
Executed rapid 100% bolted modular assembly and crane lifting with zero field welding, adhering to strict petrochemical safety standards.
Through this specialized industrial methodology, Sazeh Tadbiran delivered a high-performance storage and process hall envelope engineered for continuous operation in the Asaluyeh energy zone. The arched double-layer MERO grid provided exceptional structural stiffness and high internal clearance, allowing seamless operation of heavy industrial equipment and overhead material handling systems without interior column interference.
Upon completion, the petrochemical complex gained a robust, corrosion-proof architectural enclosure capable of withstanding extreme temperatures and aggressive chemical environments for decades.
During the final commissioning phase, our QA/QC engineers conducted comprehensive ultrasonic weld verifications, coating micron-thickness tests, and bolt torque inspections, achieving full HSE approval and timely handover.
In petrochemical zones like Asaluyeh, extreme corrosive humidity and strict HSE restrictions against on-site welding make large-span roof construction highly challenging. Sazeh Tadbiran’s 100% bolted MERO space frame system and chemical-resistant powder coating provided the ideal engineering solution—delivering a massive, column-free industrial span safely, rapidly, and with zero hot-work risks.